|
Permits,
Safety & Foundations
|
We recommend excavating the
site 4 inches deep and laying gravel or crushed rock where drainage
may be a concern.
Foundations
Recommendations:
We recommend 3 different
methods for constructing basic foundations for the cedar sheds:
1. Patio Stones
2. 4x4 Pressure Treated Beams
3. Concrete Slab
Laying Out The Foundation
No matter which type of
foundation you’ve chosen, start by outlining the
"footprint" on the site. Start by choosing one corner of
the garden shed or the center of gazebo and mark it (A) by driving a
stake into the ground.
Garden Sheds
Stretch a line from stake a
straight across C and fasten it to a temporary stake outside the
intended garden shed area. Measure along this line from A and mark
the garden shed dimension in that direction. Drive a stake there and
set up batter boards. Use the 3-4-5 triangulation method to extend
another line at right angles to the A-C line. Measure to the next
corner and stake it. Continue until all corners of the garden shed
are connected by right angle lines.
3-4-5 Triangulation Method
Measure along the line 3 feet
from the first stake A, and mark the string at this point. From
stake A, run a second line perpendicular to the first. Measure out 4
feet to locate point C. If this second line is exactly at a right
angle to the first, the diagonal line between A & C will be 5
feet. If not, move point C left or right until the diagonal measures
5 feet and stake that point.
Stretch a radial line from
center stake A. Calculate the radius by using 1/2 the diameter of
gazebo. Using orange spray paint or something similar, mark out a
circle.
First determine door location
by using one Rim Joist of Gazebo, stake points where rim joist
intersects circle. Move around circle staking out all intersecting
points until all corners are connected.
Determine The Type of
Foundation
1. Patio Stone Foundation
If the ground is stable and has
sufficient drainage, you can set patio stones directly on firm,
compacted soil. If not, lay on gravel or crushed rock as previously
described.
Garden Sheds: Starting with one
floor section, position stones around its perimeter and specific
joists. (For details, see specific instruction manual) Use a 2x4
straight piece of lumber on edge and a carpenter’s level to
position correctly. Add or remove soil/sand under each stone until
level. Complete remaining floor sections in the same manner. When
all floor panels are level with each other, flip over, screw
together and place back on level foundation.
Gazebo: Position patio stones
on outline of gazebo previously described. For details of how and
where stones go, see specific instruction manual. Use a 2x4 straight
piece of lumber on edge and a carpenter’s level to position
correctly. Add or remove soil/sand under each stone until level.
When stones are level, position completed sub-structure (Rim, Long
& Short Joist and Core Block) on top. Once again, use a level to
confirm positioning and make any necessary adjustments.
2. 4x4 Pressure Treated Beam
Foundation
You can build directly on
pressure-treated beams or railroad ties lay on a properly prepared
construction site. Run beams perpendicular to floor joists. Use a
2x4 straight piece of lumber on edge and a carpenter’s level to
position correctly.
To prevent the beams from
shifting, secure them with? Inch rebar inserted through holes
drilled in the beams and driven 3 to 4 feet into the ground. Leave
each side or end of the foundation open to promote drainage and air
circulation beneath the floor.
3. Concrete Slab Foundation
Typically a slab 3-4 inches
thick laid over a sub base of 4 inches of gravel or crushed rock is
sufficient but may vary depending on your geographic location.
Using either mix your own
concrete of having it delivered by truck, ready to pour, depends on
how much time and effort you have to dedicate to the project. A slab
for our 8x10 foot Rancher or a 10 foot gazebo both to a depth of 4
inches will require approximately 1 cubic yard of premixed concrete.
Use the following procedure:
1. Excavate the slab area and
footing trench.
2. Excavate the slab area to a
depth 6 inches. This would put the finished slab surface 2 inches
above ground (4 inches of gravel)
3. Set up your batter board
strings to represent the outside face of the slab. At each corner,
drop a plumb line from the intersecting strings to the bottom of the
trench, then drive a 2x4 stake at this point. Using the plumb bob
again, drive a nail into the top of the stake where the plumb bob
touches it. Attach strings between the stakes. Using the strings as
guides, drive the 2x4 form stakes around the trench perimeter,
spaced on 2 foot centers.
4. Attach the form boards to
the stakes with double-headed nails. Make sure the stakes are on the
outside of the boards and flush with or below them.
5. Use 2x4 stakes to brace the
corners of the forms.
6. Backfill the excavation with
4 inches of gravel, then lay down a plastic vapor barrier.
7. Spread or pour concrete with
a rake or hoe, compacting it gently into the footing areas. Use a
shovel to move concrete into footing trench. Make the pour to about
1 inch above the forms to allow for settling. Use a long 2x4 to
level the concrete. Move the board in a side-to-side motion as you
pull it towards you.
8. Use finishing tools, such as
a bull float and trowel, to smooth the concrete surface. Allow the
concrete to cure fully (seven to ten days).
|